Construction Updates

New Entry Road

  • The initial section of the new entry is nearing completion with the road paved, lane lines painted and finishing touches in process.  
  • The extension of the New Entry to Diamante and Resort Boulevard has commenced with site clearing, plant rescue completed and initial grading in process.

 

Homesite Updates

  • Casita Roads are now complete
  • Cardonal Villas
    • Section of road from CV16-24 has been paved. 
    • Construction has begun from CV10-15
  • Sunset Hill
    • New road sections completed between SH6-11 and SH76-78
    • Additional sections are under design and will begin in November. 
  • Beach Estates
    • BE02-08 under construction and being poured.  Schedule to be complete by Nov. 1
    • BE27-32 will begin in November. 

 

Retaining Walls

  • New retaining walls have been completed in Legacy Founders and Cardonal Villas.

  • Additional walls are in process in Legacy Villas, Cardonal Villas and Las Terrazas.

 

Beach Club

  • Earthwork and Building/pool pad preparation is ongoing.
  • Building foundations will commence in November.  
  • Updated renderings will be available this month. 
  •  

Legacy Golf Course

  • The practice facility is growing in nicely.  
  • The Short Game/Par 3 area is ready for grassing
  • Holes 10, 11 and 12 are in the final stages of being prepared for grassing
    • Irrigation is being installed, bunker construction is underway and greens construction is also in progress
    • Additional landscape planting is occurring along the perimeter of the holes as well. 
  •  The first phase of the Legacy Clubhouse has begun construction with foundation and retaining wall activities underway.

 

General Site Improvements

  • Continued effort to repair and improve roads and site conditions after recent storm events. 
  • Commencement of construction in new areas has allowed us to revegetate additional road sections throughout Diamante. 
  • Preparations for the WWT Championship have started and can be seen across Diamante.