Paving Update

We are pleased to announce that the street paving work in Section 4 has officially begun. This is the final section and once this phase is complete, all streets in Casitas Phase 2 will be fully paved and finished.

Key Details

Location:

  • Casitas 23 – 31
 
Timeline:
  • May 21–June 21, 2025: Layout, earthwork, base prep
  • June 13–21, 2025: Curb installation
  • June 19–July 10, 2025: Concrete paving (in segments to maintain home access)

 

Curing:

  • Each section requires 5 days before reopening to vehicles; roads will reopen progressively.
 
Work Hours:
  • Mon–Fri: 8:00 AM–6:00 PM
  • Sat: 8:00 AM–2:00 PM
  • Extended hours (pour days only): 7:00 AM–9:30 PM
  • No work on Sundays or holidays


Traffic:

  • Flaggers onsite to manage flow and ensure safe home access



If you have any questions or concerns regarding the paving work, please don’t hesitate to reach out. Thank you for your cooperation and support.